Scheduled Maintenance - Coventry Datacentre - Fibre Wavelength Services
Scheduled Maintenance Report for UK Servers Status
Completed
The scheduled maintenance has been completed.
Posted Sep 29, 2022 - 06:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 28, 2022 - 23:00 BST
Scheduled
During the above period one of the suppliers of wavelength services providing connectivity from our London PoPs to our Coventry datacentres will be carrying out essential maintenance work.

This work involves completing the works under a controlled change on our platform for Ciena software upgrades to ensure consistency throughout the network, enhance functionality and prevent obsolescence.

Due to the redundant nature of the UK Servers network this maintenance is not expected to be service affecting for our customers as traffic will automatically re-route on alternative paths however due to the nature of the work the network to our Coventry site should be deemed at risk during this period.

Whilst a lengthy maintenance window is scheduled to cover all eventualities the service provider does not expect the circuits to be offline for the duration of the maintenance window and UK Servers customer's services should not be affected.
Posted Aug 26, 2022 - 19:50 BST
This scheduled maintenance affected: Coventry (DH1) and Coventry (DH2).