Power Maintenance - Rack 11 - Co-Located Servers - Coventry Datacentre
Scheduled Maintenance Report for UK Servers Status
Completed
The scheduled maintenance has been completed.
Posted Jun 09, 2021 - 04:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 09, 2021 - 03:00 BST
Scheduled
UK Servers have identified a fault with a power distribution unit which is going to be replaced during the following maintenance window. A number of customers with co-located servers in this rack with single non redundant power supplies will have their servers powered down for this work. We expect the PDU replacement to take less than five minutes and updates will be posted to this page once the maintenance has been completed.
Posted Jun 04, 2021 - 15:58 BST
This scheduled maintenance affected: Coventry (DH1).